More than 400 new homes created in Hartlepool over the last year according to official figures
More than 400 new properties have been delivered in Hartlepool over the last year according to official figures – with more on the way.
Hartlepool Borough Council has a housing delivery target of 400 new homes per year as part of the area’s local plan development blueprint.


This is higher than the “objectively assessed need” identified by the plan of 287 properties per annum to take into account replacements for demolitions, previous under-delivery and Tees Valley Combined Authority aspirations.
As part of the latest monitoring report for Hartlepool, covering 2024-25, council officers highlighted these targets were exceeded and a net total of 470 properties were delivered over the year.
This included 467 new builds and three buildings undergoing a change of use.
Kieran Bostock, director for neighbourhoods and regulatory services, said it was a “very positive trend” and continues the strong performance seen last year when a net total of 585 properties were delivered.
Officers noted the cumulative under-delivery during the 2018 local plan period continues to decline and now sits at minus 36 compared to minus 106 just 12 months prior.
The latest meeting of the Neighbourhoods and Regulatory Services Committee heard there were a total of 166 new starts in 2024/25.
These were mainly from sites at Wynyard, Upper Warren, Marine Point, Quarry Farm 2, Elwick Park, Antler Park and Woodside Meadows Seaton.
Housing growth in 2024-25 included the delivery of 93 affordable homes, above the council’s local plan target of 74.
A total of £363,000 in financial contributions from developers to councils to help mitigate the impact of developments was also received for off-site affordable housing over the past year.