New survey says Hartlepool's sports hall facilities will be 'adequate to meet future demand' after Mill House leisure centre closure
Hartlepool's sports hall provision will be "adequate to meet future demand" even after the closure of the town’s Mill House Leisure Centre, according to a new study.
The findings have come from a refreshed indoor facilities strategy which seeks to ensure the right sports and leisure facilities are provided in the right places.
The study has been carried out by Max Associates on behalf of Hartlepool Borough Council.
It found the existing provision of sports halls is “adequate to meet future demand, even after accounting for the closure of Mill House Leisure Centre” and the council “does not need to provide additional sports hall space”.


Mill House will be shutting its doors in the spring of 2026 following the opening of the new Highlight active wellbeing hub on the former Jackson’s Landing site.
Yet the new facility will not provide sports hall facilities for sports such as five-a-side football, basketball and netball.
The findings ruled there will still be “sufficient space in the town, provided by the council, schools and other partners” to meet the future needs of residents.
It stated Hartlepool will have 15 sports halls across 11 sites, with public access to facilities provided by a number of schools along with sports and youth centres at Brierton, Headland, Rossmere, Throston and Belle Vue.
The report acknowledged there is a need for the council “to work with education partners to develop community use agreements to protect and where possible increase access” to facilities.
It also stated the council needs to ensure ageing stock is refurbished to retain availability.
Meanwhile, it is recommended the council work with local clubs “where there has been a significant recent growth in demand” to support them to “develop their own venues”.
Facilities as part of the new Highlight leisure centre will include a 25m 8-lane main pool, a 25m 4-lane learner pool and a leisure pool.
The report found the council “may need to consider additional water space in future years” to meet demand from population growth beyond 2033 or if availability at the current sites reduce.
Representatives from Max Associates noted if this was the case it would likely be a “small community use pool” is needed.
The strategy was approved at the latest meeting of the council’s housing, growth and communities committee.